Gas-lift increment — major operator
The challenge
Three offshore gas-lift wells in the offshore field needed their wellheads rebuilt from the casing up. The existing casing head and spool had to be removed and three concentric casing strings — 18-5/8", 13-3/8" and 9-5/8" — recovered, re-stubbed and re-terminated, all on a live platform working to a tight drilling-rig schedule.
The IWS approach
Working to a written reconstruction procedure prepared for the end operator (the end operator), the crew cut access windows in the outer casing, recovered the old head and re-stubbed each string with new casing pups. Every joint was butt-welded to a qualified weld map under controlled electrical preheat, then verified by non-destructive examination. A new casing head was prepared offline, welded to a fresh stub, nitrogen pressure-tested, and lifted into place — with dummy-run casing-hanger checks confirming centralisation before final welding and pressure testing.
The outcome
All three wellheads were reconstructed, pressure-tested and handed back ready for BOP nipple-up, with complete heat-treatment, visual, MT and pressure-test records. The repeatable window-cut and re-stub method let the platform move from well to well without bringing in replacement casing strings.
- Scope3 wells reconstructed
- Strings18-5/8" · 13-3/8" · 9-5/8"
- MethodWindow-cut & re-stub
- VerificationVT · MT · N₂ pressure test